Capital Improvements

Six Year Capital Improvement Plan
Annually, the City of Grosse Pointe reviews and updates its six year capital improvement plan in May.  It is then presented to City Council for review.  During the City's annual budgetary process, the capital improvement plan for the upcoming budgetary year is incorporated and adopted with the City's annual budget.


The 2022 - 2028 Capital Improvement Plan was presented to City Council on May 9, 2022 :
2022 - 2028 Capital Improvement Plan


The 2022 Capital Improvement Presentation was presented to City Council on May 9, 2022 :
2022 Annual Capital Improvement Presentation



Road Improvements

Comprehensive Road Improvement Program
In August of 2014, residents approved a new road millage of up to 2.5 mills annually.   The program is now entering into its eighth year and is showing results.

          City of Grosse Pointe's Road Improvement Program - 8 Years of Progress Charted

8 Year - Road Surface Condition Trend


2022 Road Construction Projects
Each project will be scheduled  to begin this summer.  Proposed projects and updates can be viewed below:
Rivard
- Maumee to Jefferson & Kercheval to Charlevoix
Fisher Road - Waterloo to Mack

Cranford Lane

2022 - 2027 Street Capital Improvement Presentation:     2022-2027 Presentation



2022 Road Construction Updates
The City of Grosse Pointe will provide weekly project status updates that will be distributed to property owners every Friday for the duration of each project.   If you would like to receive the following updates by e-mail, you can request to be added to the distribution list by e-mailing Christopher Hardenbrook at chardenbrook@grossepointecity.org.

Rivard Road Construction - Maumee to Jefferson & Kercheval to Charlevoix:
October 21, 2021 Project Update
April 7, 2022 Project Start Update

April 22, 2022 Project Update
April 27, 2022 Project Update
May 6, 2022 Project Update
May 13, 2022 Project Update
May 20, 2022 Project Update
May 27, 2022 Project Update
June 3, 2022 Project Update
June 10, 2022 Project Update
June 17, 2022 Project Update
June 22, 2022 Project Update
June 24, 2022 Project Update
June 27, 2022 Project Update - Jefferson to Maumee
July 1, 2022 Project Update - Jefferson to Maumee
July 1, 2022 Project Update - Kercheval to Charlevoix


Rivard Street Repair Project
In 2021, Pro-Line Asphalt Paving of Washington, Michigan was unable to complete the work the City contracted. The remaining work to resurface Rivard Boulevard, from Jefferson Avenue to Maumee Avenue and from Kercheval Avenue to Charlevoix, is in process.  Pro-Line Asphalt Paving anticipates the project to take about 8 to 10 weeks to complete.  This project includes the removal and replacement of concrete curb and gutters, driveway approaches, milling off the existing asphalt surface, joint and base repairs to the existing roadway base, and the placement of a new asphalt wearing surface.

There will be no parking on Rivard between Jefferson and Maumee and Kercheval to Charlevoix during work hours of 7am to 5pm Monday - Friday. Traffic will be restricted to residents only on all three blocks.

Removal of the asphalt layer of pavement has been completed from Jefferson to Maumee and upon review of the underlying concrete base, it has been identified that extensive deterioration exists with the underlying concrete and will require removal and replacement with a new base prior to placing asphalt.  It is anticipated, weather dependent, that the base work will commence the week of July 4.  Pro-Line Asphalt will be cleaning up the site and adjusting barricading for the holiday weekend.  During the holiday weekend and until base work commences, parking can take place on the street where areas are not barricaded off to traffic.

Pro-Line Asphalt is scheduled, weather dependent, to place asphalt on Thursday, July 7 on Rivard from Kercheval to Charlevoix. Therefore, prior to 7:00am on Thursday, July 7, all vehicles must be removed from the street and from your driveways as Rivard will be closed to all traffic starting during the asphalt paving operation. Once paving is complete in the evening, Rivard will be reopened back to traffic.  Please turn off automatic lawn irrigation systems starting the evening of Wednesday, July 6 and can be turned back on once paving operations are complete to prevent water from being on the roadway.


Dan K’s Landscaping has been regularly watering the newly placed sod and will complete their final watering on July 1 as the sod has now rooted.  Property owners are now responsible for watering the new sod that has been placed.  It has been noted there are certain areas of missing or inadequate restoration that will be addressed by the restoration subcontractor once road work is completed.

Garbage pickup, mail delivery, and parcel delivery will not be interrupted. Please continue to place garbage at the curb on your regular day for pickup.

For questions or concerns during the duration of the project, please contact Mr. Ryan Kern, Project Manager with the City’s engineering consultant, Anderson, Eckstein and Westrick, Inc. (AEW) at 586-854-5044, or by e-mail at rkern@aewinc.com.  AEW will also have a construction observer on site for the entire duration of the project.


Fisher Road - Waterloo to Mack



Cranford Lane




Mack Avenue Corridor Improvement Plan
For additional information about this project, please visit mackaveplan.com.

Mack Avenue Zoning Map Amendments
ZONING MAP AMENDMENTS – MACK AVENUE
The Grosse Pointe Planning Commission held a public hearing to consider the proposed map amendments to the Official Zoning Map. The proposed map amendments consist of parcels of land located immediately south of Mack Avenue between Cadieux and Fisher Roads was approved.

Please CLICK HERE to view the new map with the ordinance # and date that it was adopted
.



Project Updates:

     11/11/2019       

 



Public Safety and Public Services Facilities Projects

Public Works Facility Project   Click here for updates
Public Safety Facility Project   Click here for updates